# Order third-party reports

How to work this file: do each step marked "agent" yourself, unless the step says to ask first. At each step marked "person", stop, tell me what the person must do, and wait until I say it is done.
Keep my firm's files on my machine. Do not upload them anywhere.

## What it is

Scope, engage and schedule the Phase I, condition report, survey, zoning report, any specialty study and the lender's appraisal so each lands before its deadline, in the right client's name and with the right reliance parties. It ends when each report is delivered, checked for form and logged.

## Status

- Review: AI-drafted
- Sources checked: 2026-11-13
- Coverage: Federal + Texas
- This file: the syndication structure, industrial property. 13 steps; an agent can do 11 of them.

## Steps

### Step 01. List each report and the date it is needed

Who: agent. Do this step.

From the signed contract and the deadline calendar built when it was signed, list every report the deal needs: the Phase I, the property condition assessment, the survey, the zoning report, any specialty study and, if the deal is financed, the lender's appraisal and flood determination. Against each, write the date it must be in hand: the survey before the title and survey objection deadline; the Phase I, condition and zoning reports before the feasibility period ends; the appraisal and any reliance letters before the lender's commitment or closing checklist needs them. Leave time before each date to read the report and act on it. Start a tracker with one row per report: vendor, scope, client, reliance parties, ordered, site visit, draft due, final due, need-by date and status. Hand it to the principal.

- Waits on: nothing; it can start first
- Sources: common practice, with no public source to cite

### Step 02. Collect the reports and records that already exist

Who: agent. Ask first: say what you are about to do, and wait for my yes. Ask again each time.

Ask the seller, under the contract's delivery clause, for every prior Phase I and Phase II, tank and spill records, any state closure or no-further-action letter, prior surveys, condition reports, zoning letters and certificates of occupancy. Log what arrives in the tracker. Prior work helps scoping but does not replace the buyer's own inquiry. Under 40 CFR 312.20, an environmental report prepared for someone else counts only if it meets part 312's objectives and the buyer does its own additional inquiries; the interviews, lien search, government records review, site visit and professional's declaration must be updated within 180 days before acquisition, and the inquiry must fall within one year. Pass the prior environmental reports to the environmental professional once engaged.

- Waits on: step 01
- Rules:
  - All appropriate inquiries: what the Phase I must cover and how long it lasts (40 CFR 312.1, 312.11, 312.20, 312.21 and 312.22)
- Sources:
  - [40 CFR Part 312, Innocent Landowners, Standards for Conducting All Appropriate Inquiries](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-J/part-312)

### Step 03. Ask the lender what it orders and what it will accept

Who: agent. Ask first: say what you are about to do, and wait for my yes. Ask again each time.

If the deal is financed, ask the lender, or each lender still quoting, in writing: which reports it orders itself, which it will take from the buyer, whether it keeps an approved vendor list, the standard and scope it requires for each report, the survey certification wording and Table A items it wants, the form of reliance letter it needs, and how old a report it will accept at closing. Record the answers in the tracker beside each report. A report ordered to the lender's terms the first time is not ordered twice. If no lender is chosen yet, scope to the strictest answer received and note that choice.

- Waits on: step 01
- Sources: common practice, with no public source to cite

### Step 04. Decide whose name each report is in and who may rely on it

Who: agent. Do this step.

The environmental inquiry serves the person seeking the landowner protections, the one taking title. Under 40 CFR 312.1 and 312.20 the inquiry is done by or for that person; a report made for someone else counts only after the acquirer's own inquiries and the 180-day updates. So name as client the entity that will take title, or have the consultant add it before closing if the contract will be assigned to it. For each report, list the reliance parties: the lender, the title insurer for the survey, and any affiliate that will hold title. Note which consultants charge for reliance or limit it, and record the plan in the tracker for the engagement letters.

- Waits on: step 03
- Rules:
  - All appropriate inquiries: what the Phase I must cover and how long it lasts (40 CFR 312.1, 312.11, 312.20, 312.21 and 312.22)
- Sources:
  - [40 CFR Part 312, Innocent Landowners, Standards for Conducting All Appropriate Inquiries](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-J/part-312)

### Step 05. Write the Phase I scope

Who: agent. Do this step.

Ask for a Phase I to ASTM E1527-21, or E2247-23 for forestland or rural property; 40 CFR 312.11 recognizes both. The inquiry must be done by, or under the responsible charge of, an environmental professional as 40 CFR 312.10 defines one: for example, a state professional engineer or geologist license with three years of relevant full-time experience, an engineering or science degree with five, or ten years of experience. The report must give the professional's opinion, the data gaps and their significance, and the professional's qualifications, and carry the signed declaration 312.21(d) prescribes. ASTM standards are paid; rely on what the consultant's proposal says they cover. List in writing any work the buyer or lender wants beyond the standard practice, such as asbestos, lead-based paint, radon, mold, wetlands or emerging contaminants, and ask which are included.

For industrial property: Past manufacturing, plating, fueling or solvent use, or any tank, makes a follow-on Phase II more likely; ask the consultant now how it would scope and price sampling, so a Phase II can start without a new search for a firm.

- Waits on: steps 02, 04
- Rules:
  - All appropriate inquiries: what the Phase I must cover and how long it lasts (40 CFR 312.1, 312.11, 312.20, 312.21 and 312.22)
- Sources:
  - [40 CFR Part 312, Innocent Landowners, Standards for Conducting All Appropriate Inquiries](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-J/part-312)
  - [ASTM E1527-21, Standard Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process](https://store.astm.org/e1527-21.html)

### Step 06. Write the property condition assessment scope

Who: agent. Do this step.

Ask for a property condition assessment to ASTM E2018-24 and have the consultant state in its proposal what that scope covers and excludes; the standard is paid, so do not work from a summary of it. Name the buildings, systems and share of tenant spaces to be entered, the documents the seller will provide, and any add-ons the deal needs, such as roof cores, an infrared roof scan, a sewer line camera or an accessibility review. Ask for costs split into immediate repairs, near-term repairs and a reserve table over a stated term, listing each component's cost, useful life and age or remaining life, so the table can be run through the replacement-reserves calculator, which takes age (useful life less remaining life).

- Waits on: step 04
- Sources:
  - [ASTM E2018-24, Standard Guide for Property Condition Assessments: Baseline Property Condition Assessment Process](https://store.astm.org/e2018-24.html)

### Step 07. Write the survey scope and certification list

Who: agent. Do this step.

Ask for an ALTA/NSPS Land Title Survey to the 2026 standards, effective February 23, 2026, which set the fieldwork, the plat, the optional Table A items and the certification. Name the Table A items wanted, agreed with the lender and the title company, and list who the survey is certified to: the entity taking title, the lender and the title insurer. Send the surveyor the title commitment and every recorded exception document. A site surveyed before still needs a current survey: a so-called update is a new survey certified to current conditions. In Texas, only a person registered, licensed or certified under Occupations Code chapter 1071 may practice professional surveying.

- Waits on: step 04
- Rules:
  - ALTA/NSPS land title surveys: the 2026 standards apply (Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys (2026), American Land Title Association and National Society of Professional Surveyors)
- Sources:
  - [ALTA/NSPS Land Title Survey Standards](https://www.alta.org/topics/topic-land-survey-standards)
  - [The 2026 Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys](https://amerisurv.com/2026/02/01/the-2026-minimum-standard-detail-requirements-for-alta-nsps-land-title-surveys/)
  - [Texas Occupations Code, Chapter 1071 (Section 1071.251, Registration, license, or certificate required)](https://tcss.legis.texas.gov/resources/OC/htm/OC.1071.htm)

### Step 08. Write the zoning report and specialty study scopes

Who: agent. Do this step.

Decide whether the zoning confirmation will be a letter from the city, a report from a zoning vendor, or both, as the lender requires. Ask that it state the district, whether the current use is permitted, conditional or nonconforming, parking and setback compliance, open code violations and the certificates of occupancy on file. List any specialty study the business plan depends on and scope it in writing: a geotechnical report for an expansion, a wetlands delineation, an asbestos survey before renovation, a roof or structural study the condition consultant recommends, or a market study for a lease-up. Give each specialty study its own row in the tracker with its need-by date.

For industrial property: Have the zoning report confirm outdoor storage, truck parking and the specific industrial use where the business plan relies on them; slab, pavement and fire-protection capacity for the planned storage may need a specialist beyond the condition report.

- Waits on: step 04
- Sources: common practice, with no public source to cite

### Step 09. Get proposals and check each provider's license

Who: agent in a browser. Ask first: say what you are about to do, and wait for my yes. Ask again each time.

Send each scope to the lender's approved firms or, without a list, to more than one firm, and ask for a written proposal stating the scope, exclusions, turnaround, fee, insurance, limit of liability and reliance terms. Compare them line by line in the tracker and mark any proposal whose delivery date misses the need-by date. Look up each surveyor on the Texas Board of Professional Engineers and Land Surveyors' public roster and record the registration number and status. Check the environmental professional's stated qualifications against 40 CFR 312.10. Hand the comparison to the principal.

- Waits on: steps 05, 06, 07, 08
- Rules:
  - All appropriate inquiries: what the Phase I must cover and how long it lasts (40 CFR 312.1, 312.11, 312.20, 312.21 and 312.22)
- Sources:
  - [Texas Occupations Code, Chapter 1071 (Section 1071.251, Registration, license, or certificate required)](https://tcss.legis.texas.gov/resources/OC/htm/OC.1071.htm)
  - [Land Surveyor Roster](https://pels.texas.gov/roster/ls_rosters.html)
  - [40 CFR Part 312, Innocent Landowners, Standards for Conducting All Appropriate Inquiries](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-J/part-312)

Not in this view: for the JV structure, the step "Get the capital partner's sign-off on firms and scopes" (person online, investor) comes after this step.

### Step 10. Sign the engagement letters and pay the retainers

Who: person online, principal. Stop here: tell me what the person must do, and wait.
Gates: signature, hard to undo.

A principal picks each firm and signs its engagement letter after checking that the letter names the right client, matches the agreed scope and turnaround, lists the reliance parties or the terms for adding them, and states its limit of liability. Pay any retainer the letter requires. Record the signing date and the promised delivery dates in the tracker, and send each firm its site contact.

- Waits on: step 09
- Sources: common practice, with no public source to cite

### Step 11. Have the lender order the appraisal and flood determination

Who: person online, lender. Stop here: tell me what the person must do, and wait.

Under the federal banking agencies' appraisal rules (for the OCC, 12 CFR 34.45), a regulated lender engages a fee appraiser directly or through its agent, or accepts one engaged by another financial services institution if it conforms; the agencies' guidelines say a borrower-ordered appraisal violates those rules. So the buyer does not order it. A commercial real estate loan of $500,000 or less needs only an evaluation (12 CFR 34.43). Federal law also has regulated lenders use the standard flood hazard determination form (42 U.S.C. 4104b). Ask the lender to order both as soon as the application allows, and give it the access contact and the documents the appraiser asks for. Lenders outside these rules set their own requirements; get them in writing.

- Proof to keep: Appraisal
- Waits on: step 03
- Rules:
  - Federal appraisal threshold for commercial real estate loans: $500,000 (12 CFR 34.42, 34.43(a)(13), (b) and (d)(2); 12 CFR 225.63; 12 CFR 323.3 (implementing title XI of FIRREA))
  - Flood insurance is required on federally regulated loans in special flood hazard areas (42 U.S.C. 4012a(b))
- Sources:
  - [12 CFR 34.45, Appraiser independence](https://www.ecfr.gov/current/title-12/chapter-I/part-34/subpart-C/section-34.45)
  - [Interagency Appraisal and Evaluation Guidelines (75 FR 77450, December 10, 2010)](https://www.federalregister.gov/documents/2010/12/10/2010-30913/interagency-appraisal-and-evaluation-guidelines)
  - [12 CFR 34.43, Appraisals required; transactions requiring a State certified or licensed appraiser](https://www.ecfr.gov/current/title-12/chapter-I/part-34/subpart-C/section-34.43)
  - [42 U.S.C. 4104b, Standard hazard determination forms](https://www.law.cornell.edu/uscode/text/42/4104b)

### Step 12. Schedule site visits and track every delivery

Who: agent. Ask first: say what you are about to do, and wait for my yes. Ask again each time.

Book each site visit through the contract's access clause and the seller's contact, giving tenants the notice their leases require, and send the seller any insurance certificate it asks of the consultants. Send the environmental professional the buyer's own inquiry answers before its visit. Each week, update the tracker from the firms' confirmations and flag any report whose expected delivery now falls after its need-by date. Tell the principal the same day a date slips, with the contract date at risk, so an extension or a narrower scope can be sought before the deadline rather than after it.

- Waits on: steps 10, 11
- Sources: common practice, with no public source to cite

### Step 13. Check each report's form on delivery and log it

Who: agent. Do this step.

On receipt, check form, not findings: right property and legal description, right client and reliance parties, the standard named, signed and dated. The Phase I must carry the professional's opinion, data gaps, qualifications and signed declaration (40 CFR 312.21). The survey must carry the agreed Table A items and certification list. Record the appraisal's client, intended use, interest appraised and effective date. Send errors back at once. Enter the Phase I's expiry in the deadline calendar: the inquiry must fall within one year before acquisition, and the interviews, lien search, records review, site visit and declaration within 180 days, so a slipping closing needs an update. Whether an existing appraisal still holds is the lender's call. File each report and hand it to whoever runs due diligence.

- Proof to keep: Phase I environmental site assessment, Property condition assessment, Survey, Zoning report, Appraisal
- Waits on: step 12
- Rules:
  - All appropriate inquiries: what the Phase I must cover and how long it lasts (40 CFR 312.1, 312.11, 312.20, 312.21 and 312.22)
  - ALTA/NSPS land title surveys: the 2026 standards apply (Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys (2026), American Land Title Association and National Society of Professional Surveyors)
- Sources:
  - [40 CFR Part 312, Innocent Landowners, Standards for Conducting All Appropriate Inquiries](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-J/part-312)
  - [Interagency Appraisal and Evaluation Guidelines (75 FR 77450, December 10, 2010)](https://www.federalregister.gov/documents/2010/12/10/2010-30913/interagency-appraisal-and-evaluation-guidelines)

## Rule cards

### All appropriate inquiries: what the Phase I must cover and how long it lasts

Rule `us-fed.epa.all-appropriate-inquiries` · Federal

To claim CERCLA's innocent landowner, contiguous owner or bona fide prospective purchaser protection, a buyer conducts all appropriate inquiries before taking title: an environmental professional's inquiry plus the buyer's own cleanup-lien search, specialized knowledge and check of price against uncontaminated value. ASTM E1527-21, or E2247-23 for forestland or rural property, is a recognized way to comply. The inquiry must fall within one year before acquisition, and the interviews, lien search, records review, site visit and declaration within 180 days.

- Law: [40 CFR 312.1, 312.11, 312.20, 312.21 and 312.22](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-J/part-312)
- As of 2026-11-09; sources checked 2026-11-12; AI-drafted
- Watch for: EPA amendments to Part 312 or to the ASTM standards it recognizes; E1527-13 stopped qualifying on February 13, 2024 and E2247-16 on June 24, 2025.
- Sources:
  - [40 CFR Part 312, Innocent Landowners, Standards for Conducting All Appropriate Inquiries](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-J/part-312). Office of the Federal Register (eCFR), opened 2026-11-12, primary source.
  - [Brownfields All Appropriate Inquiries](https://www.epa.gov/brownfields/brownfields-all-appropriate-inquiries). U.S. Environmental Protection Agency, opened 2026-11-12, primary source.

### ALTA/NSPS land title surveys: the 2026 standards apply

Rule `us-fed.alta-nsps.survey-standards` · Federal

The 2026 Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys, an industry standard adopted jointly by ALTA and NSPS rather than a statute, took effect February 23, 2026 and replaced the 2021 edition. A survey contracted on or after that date follows the 2026 standards, with very limited exceptions. The request names a 2026 ALTA/NSPS Land Title Survey and the optional Table A items wanted. Where a state's minimum standards are stricter, the surveyor meets those too.

- Law: [Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys (2026), American Land Title Association and National Society of Professional Surveyors](https://www.alta.org/topics/topic-land-survey-standards)
- As of 2026-11-12; sources checked 2026-11-12; AI-drafted
- Watch for: The next joint ALTA/NSPS revision; the standards are revised about every five years.
- Sources:
  - [ALTA/NSPS Land Title Survey Standards](https://www.alta.org/topics/topic-land-survey-standards). American Land Title Association, opened 2026-11-12, primary source.
  - [2026 ALTA/NSPS Standards](https://nsps.us.com/page/2026ALTA). National Society of Professional Surveyors, opened 2026-11-12, primary source.

### Federal appraisal threshold for commercial real estate loans: $500,000

Rule `us-fed.firrea.appraisal-thresholds` · Federal

Institutions regulated by the OCC, the Federal Reserve and the FDIC need an appraisal by a state certified or licensed appraiser for real estate-related financial transactions, with exceptions. A commercial real estate transaction of $500,000 or less is excepted; the institution obtains an evaluation instead. Above $500,000, a commercial real estate transaction needs a state certified appraiser. Commercial means not secured by a single one-to-four family residence, so multifamily counts; for a loan, transaction value is the loan amount.

- Law: [12 CFR 34.42, 34.43(a)(13), (b) and (d)(2); 12 CFR 225.63; 12 CFR 323.3 (implementing title XI of FIRREA)](https://www.ecfr.gov/current/title-12/chapter-I/part-34/subpart-C/section-34.43)
- As of 2026-11-09; sources checked 2026-11-12; AI-drafted
- Watch for: A joint rule by the OCC, Federal Reserve and FDIC changing the appraisal thresholds; 12 CFR 34.43 was last amended in 2019.
- Sources:
  - [12 CFR 34.43, Appraisals required; transactions requiring a State certified or licensed appraiser](https://www.ecfr.gov/current/title-12/chapter-I/part-34/subpart-C/section-34.43). Office of the Federal Register (eCFR), opened 2026-11-12, primary source.
  - [12 CFR 34.42, Definitions](https://www.ecfr.gov/current/title-12/chapter-I/part-34/subpart-C/section-34.42). Office of the Federal Register (eCFR), opened 2026-11-12, primary source.
  - [12 CFR 34.41, Authority, purpose, and scope](https://www.ecfr.gov/current/title-12/chapter-I/part-34/subpart-C/section-34.41). Office of the Federal Register (eCFR), opened 2026-11-12, primary source.
  - [12 CFR 225.63, Appraisals required; transactions requiring a State certified or licensed appraiser (Federal Reserve)](https://www.ecfr.gov/current/title-12/chapter-II/subchapter-A/part-225/subpart-G/section-225.63). Office of the Federal Register (eCFR), opened 2026-11-12, primary source.
  - [12 CFR 323.3, Appraisals required; transactions requiring a State certified or licensed appraiser (FDIC)](https://www.ecfr.gov/current/title-12/chapter-III/subchapter-B/part-323/subpart-A/section-323.3). Office of the Federal Register (eCFR), opened 2026-11-12, primary source.

### Flood insurance is required on federally regulated loans in special flood hazard areas

Rule `us-fed.flood.mandatory-purchase` · Federal

A federally regulated or federal agency lender may not make, increase, extend or renew a loan secured by improved real estate in a special flood hazard area where federal flood insurance is available unless the building and any personal property securing it carry flood insurance for the loan's term of at least the lesser of the principal balance and the program's maximum for that property type. Loans Fannie Mae or Freddie Mac buy must comply. Qualifying private policies count.

- Law: [42 U.S.C. 4012a(b)](https://www.law.cornell.edu/uscode/text/42/4012a)
- As of 2026-11-12; sources checked 2026-11-12; AI-drafted
- Watch for: Amendments to 42 U.S.C. 4012a or to National Flood Insurance Program coverage limits, and FEMA map revisions that move a property into or out of a special flood hazard area.
- Sources:
  - [42 U.S.C. 4012a, Flood insurance purchase and compliance requirements and escrow accounts](https://www.law.cornell.edu/uscode/text/42/4012a). Legal Information Institute (statute text), opened 2026-11-12, primary source.
  - [Flood Zones (glossary)](https://www.fema.gov/about/glossary/flood-zones). Federal Emergency Management Agency, opened 2026-11-12, primary source.
  - [FEMA Flood Map Service Center](https://msc.fema.gov/portal/home). Federal Emergency Management Agency, opened 2026-11-12, primary source.
  - [Types of Coverage (National Flood Insurance Program limits)](https://agents.floodsmart.gov/topics/selling-flood-insurance/coverage). FEMA National Flood Insurance Program (FloodSmart for agents), opened 2026-11-12, primary source.

## Sources

1. [40 CFR Part 312, Innocent Landowners, Standards for Conducting All Appropriate Inquiries](https://www.ecfr.gov/current/title-40/chapter-I/subchapter-J/part-312). Office of the Federal Register (eCFR), opened 2026-11-13, primary source.
2. [ASTM E1527-21, Standard Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process](https://store.astm.org/e1527-21.html). ASTM International, opened 2026-11-13, primary source.
3. [ASTM E2018-24, Standard Guide for Property Condition Assessments: Baseline Property Condition Assessment Process](https://store.astm.org/e2018-24.html). ASTM International, opened 2026-11-13, primary source.
4. [ALTA/NSPS Land Title Survey Standards](https://www.alta.org/topics/topic-land-survey-standards). American Land Title Association, opened 2026-11-13, primary source.
5. [The 2026 Minimum Standard Detail Requirements for ALTA/NSPS Land Title Surveys](https://amerisurv.com/2026/02/01/the-2026-minimum-standard-detail-requirements-for-alta-nsps-land-title-surveys/). The American Surveyor, opened 2026-11-13.
6. [Texas Occupations Code, Chapter 1071 (Section 1071.251, Registration, license, or certificate required)](https://tcss.legis.texas.gov/resources/OC/htm/OC.1071.htm). Texas Legislature, opened 2026-11-13, primary source.
7. [Land Surveyor Roster](https://pels.texas.gov/roster/ls_rosters.html). Texas Board of Professional Engineers and Land Surveyors, opened 2026-11-13, primary source.
8. [12 CFR 34.45, Appraiser independence](https://www.ecfr.gov/current/title-12/chapter-I/part-34/subpart-C/section-34.45). Office of the Federal Register (eCFR), opened 2026-11-13, primary source.
9. [12 CFR 34.43, Appraisals required; transactions requiring a State certified or licensed appraiser](https://www.ecfr.gov/current/title-12/chapter-I/part-34/subpart-C/section-34.43). Office of the Federal Register (eCFR), opened 2026-11-13, primary source.
10. [Interagency Appraisal and Evaluation Guidelines (75 FR 77450, December 10, 2010)](https://www.federalregister.gov/documents/2010/12/10/2010-30913/interagency-appraisal-and-evaluation-guidelines). Federal Register (OCC, Federal Reserve, FDIC, OTS, NCUA), opened 2026-11-13, primary source.
11. [42 U.S.C. 4104b, Standard hazard determination forms](https://www.law.cornell.edu/uscode/text/42/4104b). Legal Information Institute (statute text), opened 2026-11-13, primary source.

---

From https://www.promptedcre.com/playbooks/order-third-party-reports, computed 2026-11-23. Not legal advice: every step says where it comes from, a cited source or common practice.