Replacement reserves

Test a building's replacement reserve: the straight-line reserve per square foot or unit, the replacements due over a horizon with cost inflation, the first year the reserve runs short and the level contribution that never does.

The reserve runs short in year 10, ending it $213,435 below zero; a level $61,344 a year would not run short over 10 years.

The reserve runs short in year 10, ending it $213,435 below zero; a level $61,344 a year would not run short over 10 years.

Level contribution that never runs short

$61,344

a year, $1.022/SF; set by spending through year 10

Added contribution needed
$21,344
a year over the $40,000 given
Straight-line reserve
$40,500
a year, $0.675/SF; cost ÷ life
Replacement spending
$763,435
6 replacements in 10 years, with inflation
Lowest year-end balance
-$213,435
year 10
Balance at the end
-$213,435
end of year 10

Reserve balance

today, then each year end at $40,000 a year

Filled bars are a balance above zero; outlined bars below the line are a shortfall.

Drawn from
The worked example
Runs
In your browser
For your agent
calc_run with id replacement-reserves

Inputs

Worked example. Type over any value on a dashed line.

Building

Give the area, the unit count or both; each gives its own per-figure.

SF

blank if not used

units

blank if not used

Reserve

Example values: the inflation rate and the balances are yours to set, not a standard.

$
$/yr

added each year

%/yr

growth in replacement cost

years

1 to 50

Components

Each component's cost to replace today, its useful life when new and its age now (age = life − remaining life). An age at or past the life is replaced in year 1.

Component 1
$
years
years
Component 2
$
years
years
Component 3
$
years
years
Component 4
$
years
years
Component 5
$
years
years

The reserve, year by year.

10 years · contribution and spending fall in the year · no interest on the balance

Reserve balance by year: opening, contribution, replacements, spending and year-end balance
YearOpeningContributionReplacedSpendingYear endShort?
1$150,000$40,000HVAC units, Dock levelers$150,000$40,000no
2$40,000$40,000none$0$80,000no
3$80,000$40,000Exterior paint$53,045$66,955no
4$66,955$40,000none$0$106,955no
5$106,955$40,000none$0$146,955no
6$146,955$40,000none$0$186,955no
7$186,955$40,000Paving$107,465$119,490no
8$119,490$40,000Exterior paint$61,494$97,997no
9$97,997$40,000none$0$137,997no
10$137,997$40,000Roof$391,432-$213,435short

Each component's reserve and replacement years.

Straight-line reserve is cost today ÷ useful life

Each component's cost, life, age, straight-line reserve and the years it is replaced inside the horizon
ComponentCost todayLife, yrsAge, yrsReserve /yrReplaced in
Roof$300,0002515$12,000yr 10
HVAC units$120,0001515$8,000yr 1
Paving$90,000125$7,500yr 7
Dock levelers$30,0001012$3,000yr 1
Exterior paint$50,00052$10,000yr 3, yr 8

Every formula it ran, in order.

Year t costs today's cost × (1 + inflation)^(t − 1)

  1. 1Roof: straight-line reserve$300,000.00 ÷ 25 years$12,000.00/yr
  2. 2HVAC units: straight-line reserve$120,000.00 ÷ 15 years$8,000.00/yr
  3. 3Paving: straight-line reserve$90,000.00 ÷ 12 years$7,500.00/yr
  4. 4Dock levelers: straight-line reserve$30,000.00 ÷ 10 years$3,000.00/yr
  5. 5Exterior paint: straight-line reserve$50,000.00 ÷ 5 years$10,000.00/yr
  6. 6Straight-line reserve, totalsum over 5 components$40,500.00/yr
  7. 7Straight-line reserve per square foot$40,500.00 ÷ 60,000 SF$0.675/SF/yr
  8. 8Roof: replaced infirst year max(1, 25 − 15) = 10, then every 25 years, through year 10year 10
  9. 9HVAC units: replaced infirst year max(1, 15 − 15) = 1, then every 15 years, through year 10year 1
  10. 10Paving: replaced infirst year max(1, 12 − 5) = 7, then every 12 years, through year 10year 7
  11. 11Dock levelers: replaced infirst year max(1, 10 − 12) = 1, then every 10 years, through year 10year 1
  12. 12Exterior paint: replaced infirst year max(1, 5 − 2) = 3, then every 5 years, through year 10year 3, year 8
  13. 13HVAC units, year 1: cost$120,000.00 × (1 + 3.00%)^(1 − 1)$120,000.00
  14. 14Dock levelers, year 1: cost$30,000.00 × (1 + 3.00%)^(1 − 1)$30,000.00
  15. 15Exterior paint, year 3: cost$50,000.00 × (1 + 3.00%)^(3 − 1)$53,045.00
  16. 16Paving, year 7: cost$90,000.00 × (1 + 3.00%)^(7 − 1)$107,464.71
  17. 17Exterior paint, year 8: cost$50,000.00 × (1 + 3.00%)^(8 − 1)$61,493.69
  18. 18Roof, year 10: cost$300,000.00 × (1 + 3.00%)^(10 − 1)$391,431.96
  19. 19Replacement spending over 10 yearssum of 6 replacements$763,435.36
  20. 20Balance, end of year 1$150,000.00 + $40,000.00 − $150,000.00$40,000.00
  21. 21Balance, end of year 2$40,000.00 + $40,000.00 − $0.00$80,000.00
  22. 22Balance, end of year 3$80,000.00 + $40,000.00 − $53,045.00$66,955.00
  23. 23Balance, end of year 4$66,955.00 + $40,000.00 − $0.00$106,955.00
  24. 24Balance, end of year 5$106,955.00 + $40,000.00 − $0.00$146,955.00
  25. 25Balance, end of year 6$146,955.00 + $40,000.00 − $0.00$186,955.00
  26. 26Balance, end of year 7$186,955.00 + $40,000.00 − $107,464.71$119,490.29
  27. 27Balance, end of year 8$119,490.29 + $40,000.00 − $61,493.69$97,996.60
  28. 28Balance, end of year 9$97,996.60 + $40,000.00 − $0.00$137,996.60
  29. 29Balance, end of year 10$137,996.60 + $40,000.00 − $391,431.96-$213,435.36
  30. 30First year the reserve runs shortthe first year-end balance below zero by half a cent or moreyear 10, -$213,435.36
  31. 31Lowest year-end balancelowest over 10 years, the first year it occursyear 10, -$213,435.36
  32. 32Level contribution that never runs shortmax over years t of (spending through t − starting balance) ÷ t, set by year 10: ($763,435.36 − $150,000.00) ÷ 10$61,343.54/yr
  33. 33Level contribution per square foot$61,343.54 ÷ 60,000 SF$1.022/SF/yr
  34. 34Added contribution neededmax(0, $61,343.54 − $40,000.00 given)$21,343.54/yr

Marked: the lines your last edit changed.

For your agent: calc_run returns these same 34 lines.

How it counts, and how it is checked.

Checked by an independent calculation

How it counts

  • Each component's straight-line reserve is its cost to replace today divided by its useful life; the total is divided by the area for a figure per square foot and by the unit count for a figure per unit, and a blank area or unit count gives no figure.
  • Each component is entered with its age, which is its life less its remaining life when a reserve table lists remaining life; it is replaced in the year its age reaches its life, year max(1, life minus age) counted from today, and again every life after that inside the horizon, so one already at or past its life is replaced in year 1.
  • A replacement in year t costs today's cost times (1 + inflation) to the power t minus 1, so year 1 is priced at today's cost; inflation is an input, and the example's rate is an example, not a forecast.
  • Each year the balance is last year's balance plus the contribution less that year's spending, read at year end with no interest earned; the reserve runs short in the first year the balance is below zero by half a cent or more.
  • The level contribution that never runs short is the largest, over every year t, of the spending through year t less today's balance, divided by t, and zero when the balance covers every replacement; nothing is rounded until it is shown.

What the checks pin

  • The worked example's straight-line reserve by component, in total and per square foot, each replacement's year and inflated cost, the year-end balance for all ten years, the first shortfall, the level contribution with its year and per square foot, and the added contribution match a separate Python calculation (exact fractions, level contribution found by bisection, 2026-11-13).
  • On five plans, the ending balance equals the starting balance plus contributions less spending, the straight-line reserves sum to the total, zero inflation prices every replacement at today's cost, and the level contribution never falls as inflation rises.
  • At the level contribution no year runs short and the lowest balance is zero, while a cent a year less runs short; a balance below zero by less than half a cent is not a shortfall.
  • A component past or at its life (replaced in year 1), none inside the horizon, a starting balance that covers everything, a one-year horizon and life, per unit and per square foot are pinned; a missing area and unit count, a negative cost, a life under one year, a fractional life and unknown fields are refused in plain words.

Called by 7 steps in 6 playbooks.

For your agent

It calls calc_run with id replacement-reserves and the same inputs as the form above, and gets back the result, its working and the rule cards it rests on. The worked example is pinned in __tests__/calc-replacement-reserves.test.ts and __tests__/calc-modules.test.ts, which run it through the same function this page and the tool call.